Aterio flags nuclear power, construction gains and grid delays across U.S. data centers
Aterio’s November 2026 update says October brought bigger data center campuses, more on-site power plans and construction progress across several states. The report also highlights a transmission setback in Wisconsin that shows how grid access can still slow gigawatt-scale projects.
Why it matters: - U.S. data center growth is now tied as much to power delivery as to land and construction. - New campus plans are increasingly pairing large-scale compute with nuclear, natural gas or major utility connections. - Delays in transmission approvals can stall energization even when buildings are going up.
What happened: - Aterio released its November 2026 U.S. Datacenter Monthly update covering developments observed in October 2026. - The report tracks active, under-construction and announced data center projects across the United States. - October activity included nuclear-backed proposals, construction milestones, utility approvals and project delays in Texas, Utah, Wisconsin, Kansas, Missouri and Colorado.
The details: - Valar Atomics is proposing Project Beehive near Wellington, Utah, across more than 9,000 acres of Bureau of Land Management land. - The Utah proposal includes about 9.6 gigawatts of on-site nuclear generation. - The Project Beehive application remains under BLM review, with construction potentially starting in late 2026 and full buildout targeted for 2032. - QTS Data Centers has air permit filings for four 300-megawatt buildings in Midland, Texas, totaling about 1.2 gigawatts. - The QTS campus would use on-site natural gas generation, with phased activation targeted between late 2029 and September 2030. - Aerotropolis Industrial Development submitted a site plan for about 2.83 million square feet of data center space across 11 buildings in Aurora, Colorado. - No end user has been disclosed for the Aurora project. - Amazon is exploring a 15-building data center campus across about 890 acres in Montgomery County, Missouri. - The Missouri project remains in early planning, with land acquisition pending. - Microsoft’s Mount Pleasant campus in Wisconsin has been revised from nine planned buildings to seven. - Three Microsoft buildings are under construction in Wisconsin. - Satellite imagery shows vertical construction on Building 1 at Microsoft’s Wisconsin 2 campus. - Satellite imagery also shows foundation work and grading on Buildings 2 and 3. - xAI has begun grading the second 500-megawatt building at its planned 1-gigawatt campus in Brownsville, Texas. - xAI’s Building 1 is under structural construction, and roof installation is underway. - xAI is targeting activation for the Brownsville campus in the second quarter of 2028. - Soluna has begun construction at Project Dorothy 3A in Whitney, Texas. - Project Dorothy 3A is a joint venture between Soluna and Applied Digital, which holds 51% ownership. - Phase 1 of Project Dorothy 3A includes about 75 megawatts of gross capacity and 50 megawatts of critical IT load across a 397-acre site. - ChronoScale is the intended tenant for Project Dorothy 3A. - GPU deliveries for the project are expected in February and March 2027. - The broader Project Dorothy campus is marketed at up to 300 megawatts. - Digital Realty has grading underway at the first phase of its Astra North campus in De Soto, Kansas. - The first phase covers 281 acres. - Building 1 at Astra North has 105 megawatts approved, with completion targeted for April 2029. - Building 2 at Astra North would add 495 megawatts and remains under site plan review. - Evergy power service for Astra North is targeted for September 2028, with ramp-up to 600 megawatts by 2031. - The broader Astra North development spans 1,440 acres and targets 2 gigawatts. - ERCOT recommended conditional Public Utility Commission approval for a net metering arrangement linking Amazon’s proposed 1,200-megawatt AWS campus in Somervell County, Texas, with the 2,400-megawatt Comanche Peak nuclear plant. - Proposed energization for the Amazon campus begins at 100 megawatts in the fourth quarter of 2027. - The Amazon campus would scale to 800 megawatts by the fourth quarter of 2029 and 1,200 megawatts by the fourth quarter of 2031. - Wisconsin regulators returned the transmission line application for Project Lighthouse in Port Washington as incomplete. - Project Lighthouse is developed by Vantage Data Centers and backed by Oracle’s 1.3-gigawatt project. - Buildings are under construction at Project Lighthouse, but the campus cannot be energized until the transmission line is approved and built.
Between the lines: - The report shows a split between announced capacity and actual readiness. - Satellite imagery confirms that physical construction can advance faster than power infrastructure approvals. - Nuclear power is emerging as a major option for very large campuses, but those projects still face long timelines and regulatory review. - Natural gas generation and dedicated utility connections remain the more immediate fallback for some developers.
What's next: - Project Beehive still needs BLM review before construction can start. - QTS, Amazon and ERCOT-linked projects now depend on permitting, utility approvals and phased energization schedules. - Microsoft, xAI, Soluna and Digital Realty will need to convert construction progress into operating capacity. - Project Lighthouse’s timeline depends on a complete transmission application and eventual grid buildout.
The bottom line: - October’s data center update points to a new reality for the sector: power strategy is now a core part of project design, not just a back-end utility issue. - The winners will be the campuses that secure electricity, permits and construction progress at the same pace.
Disclaimer: This article was produced by AGP Wire with the assistance of artificial intelligence based on original source content and has been refined to improve clarity, structure, and readability. This content is provided on an “as is” basis. While care has been taken in its preparation, it may contain inaccuracies or omissions, and readers should consult the original source and independently verify key information where appropriate. This content is for informational purposes only and does not constitute legal, financial, investment, or other professional advice.
Sign up for:
Colorado Industry Wire
The daily local news briefing you can trust. Every day. Subscribe now.
Check Your Email!
We sent a one-time activation link to: .
Confirm it's you by clicking the email link.
If the email is not in your inbox, check spam or try again.
Welcome back!
is already signed up. Check your inbox for updates.